As you are aware, during construction we encountered some unanticipated subsurface conditions on Van Brunt Street that necessitated a complete redesign of the sewers and water mains. This resulted in additional work costing more than $2 million that was not in the project budget. The funding was finally made available late last year and work will resume in early May of this year.[...]Currently, all preliminary designs for the additional work have been approved, and the contractor, Trocom Construction Corporation, is engaged in securing permits, seeking out soil-disposal facilities, and making submittals which are essential prerequisites for resumption of work. The contractor plans to start work on May 10, 2010. The remaining work is expected to have a duration of six months. [Emphasis mine.]