Monday, May 3, 2010

Van Brunt Reconstruction Starts May 10th

Craig Hammerman, the district manager of of Community Board 6, lit a fire under the Department of Design and Construction regarding the long-delayed reconstruction of Van Brunt Street -- and it worked! DDC wrote to Mr. Hammerman:
As you are aware, during construction we encountered some unanticipated subsurface conditions on Van Brunt Street that necessitated a complete redesign of the sewers and water mains. This resulted in additional work costing more than $2 million that was not in the project budget. The funding was finally made available late last year and work will resume in early May of this year.

[...]

Currently, all preliminary designs for the additional work have been approved, and the contractor, Trocom Construction Corporation, is engaged in securing permits, seeking out soil-disposal facilities, and making submittals which are essential prerequisites for resumption of work. The contractor plans to start work on May 10, 2010. The remaining work is expected to have a duration of six months. [Emphasis mine.]
Thanks, Mr. Hammerman!

No comments:

Post a Comment